I have created the story and also estimation also done, but when i tried to check the Time Tracking the Estimated filed is empty. Where as if add the work Log with few min or hours it shows the logged hours but no estimated.
How to enable or make the Estimated hours visible in Time Tracking.
Example : In below two case studies.
Case 1 : No Estimation and No Remaining
Case 2: No Estimated but Remaining time is shown.
This is tied to the boards estimate settings. So if your estimate using story points, there's theoretically no need for time estimates to be shown in this context.
If you want to use that estimated field here you have to switch the boards setting to "Original Time Estimate".