Estimated time (under Time Tracking ) fields missing when estimation is done as Story Point

Kiran Rajappanavar
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
July 29, 2018

I have created the story and also estimation also done, but when i tried to check the Time Tracking the Estimated filed is empty. Where as if add the work Log with few min or hours it shows the logged hours but no estimated. 

How to enable or make the Estimated hours visible in Time Tracking. 

 

Example : In below two case studies. 

Case 1 : No Estimation and No Remaining

Case 2: No Estimated but Remaining time is shown.

JIRA.jpg

1 answer

0 votes
Andreas
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
July 29, 2018

This is tied to the boards estimate settings. So if your estimate using story points, there's theoretically no need for time estimates to be shown in this context.

If you want to use that estimated field here you have to switch the boards setting to "Original Time Estimate".

chrome_2018-07-30_08-32-52.png

Suggest an answer