How can I automate the status change of dependent issues?

John Helkenn
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
September 9, 2024

I have tasks 1, 2, and 3. 3 is dependent upon 2, which is dependent upon 1. 

All three tasks are To Do or In Progress but 1 gets blocked. How do I automate task 2 and three's status change to Blocked and send a notification email? 

Thanks!

1 answer

1 accepted

4 votes
Answer accepted
Gareth Blake-Coggins
Contributor
September 9, 2024

@John Helkenn 

You should be able to create an automation rule for the project something like the following screen shot should do what you are looking for 

Screenshot 2024-09-09 at 3.18.20 PM.png

Screenshot 2024-09-09 at 3.19.04 PM.pngScreenshot 2024-09-09 at 3.19.15 PM.pngScreenshot 2024-09-09 at 3.19.23 PM.png

John Helkenn
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
September 9, 2024

Screenshot 2024-09-09 191159.png

@Gareth Blake-Coggins Great! Thank you! It worked. Now - not all of my issues are Parent/Child, some are just linked tasks, yet this branch doesn't work. Am I missing something?Screenshot 2024-09-09 192228.png

 