Probably the time tracking field is not visible for this issue and you have to make it visible in the corresponding Field Configuration Scheme.
To track down the exact problem :
This will display possible reasons for Log Work not visible
I didn't realize that I actually needed the Time Tracking field and not Log Work on the issue for the menu items to show up. I swapped them and it's working as intended.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
I also have to state: This was confusing. The Time Tracking field is needed in Administration - Issues - View Field Configurations and your used Field Configuration. Enable Time Tracking and the "Log Work" menu point will appear. The field "Log Work" is only useful in the screens of your project, meaning, where do you want those time tracking fields to appear additionally (!) to the menu entry. Confusing and not easily solvable if you don't know how.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Earning the Mindful Member badge proves you know how to lead with kindness, plus it enters you into a giveaway for exclusive Atlassian swag. Take the quiz, grab the badge, and comment on our announcement article to spread the good vibes!
Start here
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.