Hi,
In our portfolio plan we configured several skills ( like team lead, developer, architect etc. ), but do we need to configure stages as well for using it properly, or can we use skills without stages?
Thank you!
Hi Jeroen,
Yes - you are able to use Skills without Stages.
You can break down an estimation for an issue by skill (e.g. 25% architect, 75% development). You can assign Skills to Team Members in a Plan, and Portfolio will schedule issues according to the availability of skills in the team. This can by useful for finding bottlenecks in planning introduced by work items requiring specialised experience.
Stages are more about capturing sequential activities within a work item (e.g. a design stage followed by implementation).
Thanks,
The Portfolio for Jira team.
Online forums and learning are now in one easy-to-use experience.
By continuing, you accept the updated Community Terms of Use and acknowledge the Privacy Policy. Your public name, photo, and achievements may be publicly visible and available in search engines.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.