See https://support.atlassian.com/jira-software-cloud/docs/configure-working-days/
Does AR factor this in for capacity planning and scheduling and other planning aspects?
I've been trying to get an answer but haven't been able to find one.
Also, is there any way to put in non-working days for particular team members?
I've come across this challenge recently when reviewing our plans that straddle the holiday season.
From auto-scheduling the plan after putting non-working days at the end of December it doesn't appear that AR pays any attention... although it does some odd things with scheduling generally some times so an official answer would obviously be nice.
I used to use AR when it was "Portfolio" in a Server instance where you could certainly add non-working days to the plan AND non-working days on a per team member basis. Now using Cloud I certainly can't see anywhere to do this now sadly.
Online forums and learning are now in one easy-to-use experience.
By continuing, you accept the updated Community Terms of Use and acknowledge the Privacy Policy. Your public name, photo, and achievements may be publicly visible and available in search engines.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.