Good afternoon,
I need to know how to hide any kind of issue marked as 'Cancelled' from a Jira plan. I still want to see doe example tasks or stories marked as 'Done' inside an ongoing epic but I will like to hide does issues marked as 'Cancelled'.
Thanks in advance!
It depends on how your plan is pulling the data from your Jira project. If it is a filter then have the criteria status not in (canceled, cancelled) from within the filter. You can also edit the filter on your plan board filter
for statuses--- click on status and removed checkmark from canceled and leave the check mark for the other Done category statuses.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Online forums and learning are now in one easy-to-use experience.
By continuing, you accept the updated Community Terms of Use and acknowledge the Privacy Policy. Your public name, photo, and achievements may be publicly visible and available in search engines.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.