My plan in the portfolio with all the task still to-do status. But after some task in completed/done, the task disappears in the plan.
My Portfolio Plan setting:
Estimation: days
Dependencies: Concurrent
Completed issues: 60 days
Planning interface: improved planning interface
Portfolio version: 3.5.0
Hi,
I found the problem. The resolution in completed task is still unresolve.
After add post addition to change the resolution, the completed task is reappear in plan.
Hi Tan,
Since your plan is configured with Completed issues as 60 days, Portfolio will not include all the completed issues but just the issues which are completed within the last 60 days. If you want to include more issues, you could increase this value.
Regards,
Raathi
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Steven,
The "completed issues day configuration" is in the "Issue sources" section of the configuration page.
Regards,
Raathi
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Online forums and learning are now in one easy-to-use experience.
By continuing, you accept the updated Community Terms of Use and acknowledge the Privacy Policy. Your public name, photo, and achievements may be publicly visible and available in search engines.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.