I’m new to using Jira Advanced Roadmaps and I’ve looked through documentation however I haven’t found the answer I'm looking for and hoping someone may be able to help me.
I have a plan that will be open to everyone and I want users to be able to create tasks but not fill in a start or due date field, rather an estimated hours for how long it will take to complete and have Jira automatically schedule the dates so that the start date is immediately after the previous task and the end date is based on the estimated hours to complete taking into account the teams weekly capacity. This means each task someone creates is automatically scheduled one after the other.
I know the scheduling assistant can help with certain parts of this but from what I’ve read it still seems to be based on dates that you input yourself rather than Jira figuring that out for you.
Hope that makes sense!
Any help is greatly appreciated.
Thanks,
Chloe
I've just started playing with this plugin as I have the same issue. From what I can see there is no option to put effort against an issue.
I'm certain the old version of Jira roadmaps had this functionality, bit of a shame to see it's been removed.
Online forums and learning are now in one easy-to-use experience.
By continuing, you accept the updated Community Terms of Use and acknowledge the Privacy Policy. Your public name, photo, and achievements may be publicly visible and available in search engines.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.