Hi,
we suffered a problem in the interaction between Portfolio and JIRA:
We are exclusively calculating story points in the scope view of Portfolio using the Story Point settings there. The story points are nicely summing up but (after committing the changes) don't seem to by synced with JIRA Core. Thus, they are not shown at the boards. This breaks the usage flow at JIRA Core.
My expectation would be that the story point sum in portfolio would show up in the default story point field in JIRA Core.
Is that something already being addressed?
Thanks Bernhard
The story point changes made in Portfolio does show up on the issues in Jira, however, this needs to first be committed from Portfolio. The commit option would show on the top left of the plan once the changes are made to the Story point on the plan.
Hi Mohamed,
I've indicated that the commitment were done. I will collect further indications and follow up.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Online forums and learning are now in one easy-to-use experience.
By continuing, you accept the updated Community Terms of Use and acknowledge the Privacy Policy. Your public name, photo, and achievements may be publicly visible and available in search engines.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.