Why can't I add Stories and Tasks to a Version?

Rachel Neath
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
January 23, 2019

I have enabled Versions in my Project, and I am able to drag and drop Tasks and Stories into a Version, but when I refresh the page, my changes aren't saved (i.e. Tasks/Stories I added to a Version are no longer there). 

I cannot find an option inside a Story or Task to update the Version, either. 

Am I doing something wrong?

1 comment

Comment

Log in or Sign up to comment
Carlos Garcia Navarro
Community Champion
January 27, 2019

Hi Rachel,

After moving the story/task to a version, can you see the field "Fix Versions" being populated?

When you refresh the page, is it the backlog view? Do you have the option "All issues" selected?

Screen Shot 2019-01-27 at 11.01.10 PM.png