I am using WBS Gantt Chart Plugin and want to allocate resource for same task with different rate on different dates.
Like Task A - Resource A, 100% allocation on 1st Jan, 50% allocation on 2nd Jan etc. is there any possibility?
Hello Kumar, welcome to the Community 👋🏻
Thank you for posting - Raphael from WBS Gantt-Chart support team here.
Currently, isn't possible to set different resource allocations for the same task, it will follow the same resource from the start date to the finish date of the task.
However, you can raise a ticket in our support portal and share more details from your scenario, then we can forward your feedback to our product team and they'll analyze if it's feasible for further implementation.
This should cover your needs, Kumar. If you have any comments or questions, please feel more than free to share them with us 😄
Kind Regards,
Raphael N. | Support Engineer
Ricksoft Support Team
Online forums and learning are now in one easy-to-use experience.
By continuing, you accept the updated Community Terms of Use and acknowledge the Privacy Policy. Your public name, photo, and achievements may be publicly visible and available in search engines.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.