Also curious what other people use as well.
Situation:
PM's input hours into Original Time Estimate Field in Jira.
Developers log their hours against tickets using Jira Add-On called TimeTracker.
Complications:
- Time Tracker works great against the direct ticket. It can not aggregate or roll-time up to a parent ticket.
Request from PM's - Create a Jira automation that will notify the PM's and the Sales Reps when actual developer time logged is 80% of the Original Estimated Time has elapsed.
Notifications themselves should not be a problem. Question is more to do with:
1) how would I set up automation query
2) how would your company do something like this? Any recommendations?
(Sorry if nebulous, need help with # 1 and just curious on #2 if there are better/different ways to track dev time)
I'd start with this, and debug from there
To push logged work up to the Parent Issue:
To Monitor for >80%:
I literally had a request for functionality like this yesterday. You have probably saved me hours of poking around!
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
It turns out the workRatio value (expressed as a numeral between 0 - 100, no percent sign necessary) IS this value, so a query of
workRatio > 80
is all you need :)
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Issue 1 - Complications:
- Time Tracker works great against the direct ticket. It can not aggregate or roll-time up to a parent ticket.
Approach - Time tracking should be done against sub-tasks (under all stories/tasks/bugs) so that they roll up to parent ticket. You can write an automation rule to trigger updation of estimation field of parent story/task as soon as subtask estimation is updated.
Post which you can use workratio field to check if it has reached 80.
Issue 2 -
Notifications themselves should not be a problem. Question is more to do with:
1) how would I set up automation query
2) how would your company do something like this? Any recommendations?
Approach -
1) Step 1
- Automation rule for updation of estimation field when any subtask sees change in estimation field.
- Automation rule for slack/email notification as soon as story/task has workratio >-=80
2) We don't have any such requirement. Also, I am not sure how this alert would be used by the receiver.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Recommended Learning For You
Level up your skills with Atlassian learning
Learning Path
Become an effective Jira admin
Manage global settings and shared configurations called schemes to achieve goals more quickly.
Streamline Jira administration with effective governance
Improve how you administer and maintain Jira and minimize clutter for users and administrators.
Learning Path
Become an effective Jira software project admin
Set up software projects and configure tools and agile boards to meet your team's needs.
Online forums and learning are now in one easy-to-use experience.
By continuing, you accept the updated Community Terms of Use and acknowledge the Privacy Policy. Your public name, photo, and achievements may be publicly visible and available in search engines.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.