Issue is created with Issue type which is not associated withe the project.

siva
Contributor
October 25, 2020

1.Project A doesnt have the issue type task.

But issue is created with task, any suggestions for trouble shooting ?

1 answer

1 vote
Nic Brough -Adaptavist-
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
October 25, 2020

It's not possible to do that, I suspect project A has an issue type scheme that does allow for task.

siva
Contributor
October 25, 2020

You are right, 

i have double checked the issue type  scheme, 

and the ticket is created long back which leaves me no traces how to analyze the route cause.

Thanks for the response,


Any chance you can look in this ( https://community.atlassian.com/t5/Jira-Software-questions/Need-to-add-a-condition-on-a-transition-Role-based/qaq-p/1515436)