So for example if I have an SLA that measures the time it takes for a fix version to be assigned to an issue and the SLA "Stops" on "Fix Version Assigned" and then the issue doesn't pass testing so the fix version is removed, will the "timer" start again or is the time recorded and ends when the "stop" status is reached?
condition: if u want to starts the sla on same status after stopped at same status.
Automatically it is not possible manually u have to trigger to start sla by comment base
orelse
if u want to starts the sla on different status after stopped or paused at earlier status
this can possible automatically
you have to create two sla for this one