Forums

Articles
Create
cancel
Showing results for 
Search instead for 
Did you mean: 

A sub Task to be created only 7 days before the end date.

Raj Kumar February 3, 2020

Hi,

We have a workflow transition where we have a post function to create a subtask but I want this subtask to be created only before 7days of the end date. How can we achieve this?

I tried a validator which blocks the transition until I reached 7days of the end date and then using project automation to perform the auto transition but had no luck.

 

Below is the JQL used as automation rule condition;

issuetype = "Leave of Absence" and status="Leave of Absence In Process" and "End date" >= -7d

Your earlier response is appreciated.

 

Thanks,
Raj

1 answer

0 votes
Robert Dzido _Almarise_
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
February 3, 2020

Hi,

Please note that validator is executed against main inssue, not sub-task.

To obtain your goal you can use Workflow PowerBox app. It has option to run post function based on some condition (eg. when it's less than 7 days till end date).

It also has option to run validator using JQL.

Raj Kumar February 3, 2020

Hi Robert,

Thanks for your response.

Is there a way I can do it without this app

Thanks,
Raj

Robert Dzido _Almarise_
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
February 3, 2020

Hi,

It can be possible with Automation or Script runner, but I don't have Automation for Jira installed to check it out.

Raj Kumar February 3, 2020

Hi @Robert Dzido _Almarise_ ,

Can you help me with the JQL to filter out the tickets which are due in days of the end date?

 

Thanks,
Raj

Robert Dzido _Almarise_
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
February 3, 2020

Hi @Raj Kumar ,

What do you mean by "due in days of the end date". If end date is a custom field and you want to create sub-task not more than 7 days before "end date", your condition should look like "end date" < 7d

Raj Kumar February 3, 2020

Hi @Robert Dzido _Almarise_ ,

Please find the JQL used it is not giving me the intended result can you please check and help.

Attaching screenshot for your reference.

 

In screenshot  Start date =06/03/2019 and end date= 09/16/2019 

newsub.jpg

Suggest an answer

Log in or Sign up to answer
TAGS
atlassian, aafp, jira migration, marketing collaboration, end siloed work, streamline workflows, kerrie gottschalk, jira cloud admins, unified marketing, process visibility, team efficiency, cross-team collaboration

How Kerrie Gottschalk unified AAFP’s marketing team with Jira

At the American Academy of Family Physicians, siloed marketing teams faced delays and duplicate work. Kerrie Gottschalk shook things up by moving the department to Jira, streamlining processes, boosting visibility, and sparking stronger collaboration.

Read the story
AUG Leaders

Atlassian Community Events