Burndown Chart without using Story point

kay October 28, 2019

Hi everyone, 

Our team decided not to use Story point. Nevertheless, our team would like to have a Burndown chart.

Do you perhaps know how we can have a burndown chart without story point ? 

( e.g. By the tasks that we´re working on., Progress, Stuck, done...  ) 

We´re using  server version 

2 answers

1 accepted

0 votes
Answer accepted
Ollie Guan
Community Champion
October 28, 2019

Hello @kay .

A Burndown Chart shows the actual and estimated amount of work to be done in a sprint. The horizontal x-axis in a Burndown Chart indicates time, and the vertical y-axis indicates cards (issues).

The vertical axis represents the estimation statistic that you have configured for your board.

https://confluence.atlassian.com/display/JIRASOFTWARESERVER083/Burndown+Chart

QQ截图20191028215722.png

kay October 29, 2019

Thanks for your Answer :) 

It was helpful !

1 vote
Jack Brickey
Community Champion
October 28, 2019

you can use burndown w/ time estimate. Board settings > Estimation > Original Time Estimate

Suggest an answer

Log in or Sign up to answer
TAGS
atlassian, likes for trees, atlassian community, social impact, tree planting campaign, community kudos, atlassian giving, environmental impact, sustainability, likes for good, atlassian social responsibility, community challenge

Make every click count—help us plant 50,000 trees! 🌳

Want to make your everyday Community actions directly contribute to reforestation? The Atlassian Community can achieve this goal by liking a post, attending an ACE, sending your peers kudos, and so much more!

Help us plant more trees
AUG Leaders

Atlassian Community Events