We recently stopped using story points and started using the original estimate field and remaining estimate. We have a post function on the workflow that sets remaining hours to zero upon issue closure. I switched the board configuration estimation statistic to burndown based on original estimate but nothing is happening and we've gone through two sprint cycles. I changed it to issue count and still nothing is happening. Its as if the issues are not being recognized as done. Anyone have a similar experience?
Hello,
I recommend you to check the following details:
- Make sure your done issues are properly configured with a valid resolution - The resolution is not configured as "Unresolved"
- Confirm if the statuses of your done issues are properly mapped in the last column of your board. You can check this information on Board settings > Columns.
- Check if the same problem happens if you don't use the post function to clear the Estimation
We will be waiting for your answer to know if the suggestions above helped you.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.