Calculate due date based on Original Estimate

Liz T
Contributor
November 3, 2022

Use Case: We are using the Original estimate field to estimate how long a task should take. Ex: Original estimate = 3w

We'd like the End date to update when somebody updates the Start date on a task, based on the Original estimate.
Ex: Start date 11/3/2022 + Original estimate 3w = End date  (11/24/2022)

Question: Does anybody have a suggestion on how I could create this automation?
I got this far:
>>When field value changed --start date
>>then edit issue --due date
but then don't know what to put in...I've tried various JQL, but can't get it to work.

Would this need to be a JQL or should it actually be JSON?


1 answer

1 accepted

2 votes
Answer accepted
Alex Koxaras -Relational-
Community Champion
November 3, 2022
Liz T
Contributor
November 3, 2022

Thank you!!

Liz T
Contributor
November 3, 2022 edited

@Alex Koxaras -Relational- It worked! I really appreciate your help : )

Suggest an answer

Log in or Sign up to answer
TAGS
atlassian, mindful member, mindful member badge, atlassian community, community kudos, community giveaway, atlassian swag, community values, empathy and kindness, badge challenge, atlassian learning, community engagement, swag giveaway

Earn a Badge, Win a Prize 🎁

Earning the Mindful Member badge proves you know how to lead with kindness, plus it enters you into a giveaway for exclusive Atlassian swag. Take the quiz, grab the badge, and comment on our announcement article to spread the good vibes!

Start here
AUG Leaders

Atlassian Community Events