I'm trying to schedule a transition to happen automatically after 3 days without an update but I want to ignore Saturday and Sunday as days counted. Can JJupin do this?
Hi Ethan,
Of course, you can do anything with SIL.
You should use a SIL Service doing something like this:
date auxDate = updated; number days = 0; while (auxDate < currentDate()) { if (dayOfWeek(auxDate) != "Sun" && dayOfWeek(auxDate) != "Sat") { days ++; } auxDate = auxDate + "1d"; } if (days >= 3) { //your transition here }
In order to execute the transiton you want, you can use autotransition.
Hope this helps,
Alexandra