Hi,
I want to change the value of a custom field when the sub-task of the issue was closed.
Is there an option to do that?
Thanks,
Bar
Hello,
You would need an add-on for it. What Jira version do you have (Cloud or Server)?
hi Alexey,
Thank you for your answer.
I have the Jira Server.
I think I succeed to implement this by using the post-function of the sub-task.
I added the following post-functions to one of the transitions:
First I configured the Bundle Changes field to be the expected value, and then I copied this value to the parent's field.
It this a good solution? there is maybe another way?
Thanks,
Bar
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
If you accomplished the requirement then it is fine.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Online forums and learning are now in one easy-to-use experience.
By continuing, you accept the updated Community Terms of Use and acknowledge the Privacy Policy. Your public name, photo, and achievements may be publicly visible and available in search engines.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.