A story may have several coding subtasks. Developers write "Change Info" notes when a subtask is complete.
I'm looking for a way to display in a parent task field a contatenation of all of the "Change Info" fields of the subtasks.
Ideas, anyone?
You can also use this trick: https://confluence.atlassian.com/pages/viewpage.action?pageId=163939652
This is a great solution and is now working fine. I may replace it with a scripted solution down the road, but this is nice instant gratefication.
One note, the article is not up-to-date for JIRA 6. Now it is under System > General Configuration > Advanced Settings > jira.table.cols.subtasks
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
I desperately want the same thing for issue links :(
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Create a calculated field. If you have scriptunner installed, you can go for a scripted field.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Online forums and learning are now in one easy-to-use experience.
By continuing, you accept the updated Community Terms of Use and acknowledge the Privacy Policy. Your public name, photo, and achievements may be publicly visible and available in search engines.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.