I have 2 Jira issues(as tasks), Pre-task
and Post-task
. Post-task
can be started after Pre-task
is finished, which may be expressed like this:
Pre-task [FS] Post-task
In this case, how can I set the link type of these tasks,
Pre-task FS-depends on Post-task
, or,
Post-task FS-depends on Pre-task
?
As an admin, you can create issue link types to represent this linkage from the admin interface. Once you've created them, then you can use "link issue" from the options menu on an issue to add them to issues.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
My administrator said he had not added 'FS-depends on' link type by himself manually, instead 'Gantt Chart' plug-in seemed to do.
So, I may need to know the intention of the plug-in developer.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
So they added them via an add-on, that's fine.
I'd suggest having a look at the docs for the gantt chart (but to add the links to an issue, try "add link" from the menu!)
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Online forums and learning are now in one easy-to-use experience.
By continuing, you accept the updated Community Terms of Use and acknowledge the Privacy Policy. Your public name, photo, and achievements may be publicly visible and available in search engines.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.