How to link two projects in jira with same version?

Krithica Gowri Shankar
Contributor
December 25, 2016

i wanted to have a link between two different projects, to make log efforts should be impacted vice versa if resource worked in same tasks(same Job code) in two different projects.

for eg:

Project A - Job code - 1001

Project B - Job code - 1001

If a resource logged efforts in Project A for Job code 1001, it should also reflect in Project B for job code 1001, since they both have same job code.

How to achieve this?

 

1 answer

0 votes
Nic Brough -Adaptavist-
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
December 26, 2016

Versions belong to projects, they're not global artefacts, even if you happen to give them the same tag/name.

If you need to tie things together with these "job codes", then you either need to use the job-code field you've added (and accept that versions are different by project), or keep the work together in one project, or build reporting that understands your use of versions.