We currently have 2, soon to be 3 separate scrum teams working from one overall backlog and working within the same sprint. As each team selects different stories to work on within the sprint, how can we track each team's velocity chart and sprint report separately via the reports module and not have the results commingled for reporting? I've tried a couple different basic filters at the board level, but was more interested from a reporting aspect.
Hi Pushkant
As you have found when your teams work within the same sprint the velocity and of each team is mixed together. If the two teams are not sharing the estimation approach and therefore the same story points are not allocated to work of a different level this becomes messy.
I would approach this by having the following independent boards based on the same project.
In this way you can use the reports for each Scrum board to see the velocity and sprint details.
Online forums and learning are now in one easy-to-use experience.
By continuing, you accept the updated Community Terms of Use and acknowledge the Privacy Policy. Your public name, photo, and achievements may be publicly visible and available in search engines.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.