When looking on a WBS Gantt the "Percentage Done" on the Epic (parent issue) seems to be 0% although the Children's are on 100% .
Using Auto calculate "Percent done" in the "User Preferences".
Seems like a Bug, when I click on "Outdent" it seems to be filled with the correct data, then on refresh it's going back to 0%.
Please advise.
Hello @[deleted] ,
Are you using "Use specific field" for the progress rate setting of Epic?
If you are using "Calculate with time tracking automatically" or "Calculate with specific fields automatically", the progress rate of the child issues will not be reflected in the progress rate of the parent issue.
Kind Regards,
Yasuhiro Kawamura
Ricksoft, Inc.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Join us June 26, 11am PT for a webinar with Atlassian Champion Robert Hean & Loom’s Brittany Soinski. Hear tips, stories, and get your burning questions answered. Learn how Loom makes training and enablement easier. Don’t miss it!
Register today
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.