Hi,
I have made couple of sprints long plan. Now there are leaked items which make a collateral effect on the following sprints. What would be the best way to re-plan (tooling-wise) without needing to go thru ticket by ticket and move them accordingly.
Some kind of batch operation to move all the tickets e.g. +1 sprint?
I have Advanced roadmap in use, if that helps.
To be honest this should be actively replanned by the Product Owner, not just shifted by a tool
Actually, it should be done by the team, not PO. I am just seeking options to make that easier.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Well Product Backlog Prioritisation at a chunky level = PO, the team needs to agree into inclusion in each Sprint backlog and breakdown if they wish into tasks (assuming we're doing Scrum) right? :)
When closing a Sprint Jira will automatically give the prompt on what to do with the hanging over stories, and in the backlog view you can multi-select and move tickets.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Well, you were talking about replanning, not prioritization. I agree PO is to be making the prioritization in the end (using team input).
Closing sprint will prompt yes, and you can choose to move the items, but I was more after way to move selected items distributed several sprint e.g. +one sprint as there is collateral effect.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Online forums and learning are now in one easy-to-use experience.
By continuing, you accept the updated Community Terms of Use and acknowledge the Privacy Policy. Your public name, photo, and achievements may be publicly visible and available in search engines.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.