What is the magic the JQL thing is looking for? IS EMPTY returns differently to = 0
Also it is possible to smash all 'remaining' estimates to zero when a task is closed?
Hi,
The first question regarding the issues in progress with no time estimate is:
status = "In Progress" and remainingEstimate is empty
When you use remainingEstimate = 0, it means that it has been set, either that it has had a value before and been set to 0, or that it has been explicitly set to 0. Is Empty means that the value has not been set.
You can add a post-function for the transition to the "closed" status in the workflow and then select "Update Issue Field". Select Remaining Estimate and set the value to 0.
Online forums and learning are now in one easy-to-use experience.
By continuing, you accept the updated Community Terms of Use and acknowledge the Privacy Policy. Your public name, photo, and achievements may be publicly visible and available in search engines.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.