Linking JIRA custom fields

Brooke Musat May 4, 2018

I have created 4 custom fields in JIRA (Copy due date, Copy review due date, Design, due date and design review due date) that i'd like to link in someway.

As an example, if I change the copy due date, the copy review due date, design due date and design review due dates will automatically shift/change. Similarly, if i change the copy review due date, the design due date and design review due dates will shift/change. 

Is there a way to do this? 

Here is an example of the due dates 

JIRA.PNG

1 answer

0 votes
Vickey Palzor Lepcha
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
May 4, 2018

You'd want the increment to be uniform ? Say two days increase in Copy Due Date - you'd want to psuh Copy Review Date, Design Due Date Design Review Due Date by 2 days each ?

Brooke Musat May 4, 2018

Yes

Suggest an answer

Log in or Sign up to answer
TAGS
atlassian, team '25 europe, atlassian event, barcelona 2025, jira, confluence, atlassian intelligence, rovo, ai-powered collaboration, developer tools, agile teams, digital transformation, teamwork solutions, atlassian conference, product announcements

🌆 Team '25 Europe registration is now open!

Join the largest European gathering of the Atlassian Community and reimagine what’s possible when great teams and transformative technology come together. Plus, grab your Super Fan ticket now and save over €1,000 on your pass before prices rise on 3 June.

Register now
AUG Leaders

Atlassian Community Events