I'm looking to set a date in an automation based on a custom number field called "Number of Data Classes" in business days, plus an additional 4 business days.
I'm using {{now.plusBusinessDays(4)}} but how do I add the custom field value to that?
Thanks!
kindly check this post https://community.atlassian.com/t5/Jira-Software-questions/How-to-setup-an-automation-with-2-date-fields-sum/qaq-p/2305003
i think it has the answer to your question
{{issue.yourField.plusBusinessDays(4)}}
Thanks, but i needed the total sum in business days so this ended up working
{{now.plusBusinessDays(issue.customField.plus(4))}}
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.