Possible to see Sprint Date for Stories in Epic View?

Bradley
Contributor
September 11, 2023

When you open up an Epic and are looking at the stories that are inside of it, it would be nice to also be able to see if they are in a sprint and which sprint. This would help with refinement and prioritization. 

 

So for example I pull up an Epic, I scroll down to see all the stories, tasks assigned to that Epic. I see the stories and their status. their summary, who was assigned, and if what type of issue they are.  But I can't see if which sprint they are in or were in. It would be a big help to be able to see that information. 

1 answer

0 votes
Hannes Obweger - JXL for Jira
Atlassian Partner
September 11, 2023

Hi @Bradley,

to the best of my knowledge, the issue list within an epic can't currently be configured. This being said, if you're open to solutions from the Atlassian Marketplace, there's a couple of options that should get you pretty close; see e.g. this thread for possible directions forward.

Best, Hannes

Suggest an answer

Log in or Sign up to answer
TAGS
atlassian, likes for trees, atlassian community, social impact, tree planting campaign, community kudos, atlassian giving, environmental impact, sustainability, likes for good, atlassian social responsibility, community challenge

Make every click count—help us plant 50,000 trees! 🌳

Want to make your everyday Community actions directly contribute to reforestation? The Atlassian Community can achieve this goal by liking a post, attending an ACE, sending your peers kudos, and so much more!

Help us plant more trees
AUG Leaders

Atlassian Community Events