Dear KartikA,
have you made sure that you also have the restore permission? Restore permission can be set as a global permission or at the project level.
Kind regards,
Tobias
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi there
I am not sure if you found a solution, but you should check if the issue you are trying to restore is a subtask. If it is, then you will not see the 'Restore'.. Once you Restore the parent object, then the subtask will be restored.
Hope this helps
Thanking you