How can we connect bugs appeared after a certain sprint or story with that sprint/story?

Oana Moldovan
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
May 7, 2019

Sometimes after launching a certain task you might notice you broke something in the process. We would really like to keep these things in track.

So at the end of a sprint we will have a chart or some stats like: bugs solved in the process versus new bugs (bugs created in the process). 

+ we would like to know that bugs x,y,z  were 'launched' because of this story/task. 

How do you suggest we do that?

Thank you!

1 answer

1 accepted

0 votes
Answer accepted
Tyler Brown
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
May 7, 2019

Hey Oana,

I would suggest creating a new link type.

This guide should help: https://confluence.atlassian.com/adminjiraserver073/configuring-issue-linking-861253998.html

You may also need the assistance of a System Administrator if you are not one.

Tyler