Hi there,
I noticed the burndown chart is showing a flat line at night (because that's when we're not productive). It looks strange and actually it's not our real burndown. Can I set it so it will only count at daytime? Would be nice...
Thanks for your help.
Cheers,
Jodi
I'm having exactly the same problem, working hours are setup (8 per day, 5 days per week), but still the burndown chart counts nighttime (we have to end our working day well below the indication line, else we start above it the next day)
Any help?
Yes, I configured only working days of course, but it's also showing the burndown at night:
Screen Shot 2015-12-14 at 20.54.05.png
So, all those flat lines are at night. I don't want JIRA to show the nighttime, because we're not working. I only want the burndown chart to count between 9 AM - 6 PM.
Hope you guys can help me. Bye,
Jodi
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You can check your working days setting by going to Board > Configure > Working Days.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
What have you configured for a working day in JIRA and or TEMPO if you are using it... Possibly related...
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Online forums and learning are now in one easy-to-use experience.
By continuing, you accept the updated Community Terms of Use and acknowledge the Privacy Policy. Your public name, photo, and achievements may be publicly visible and available in search engines.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.