I have three fields
I want value of "Expected End Date/Time" as "Task Start Date/Time + Original Estimate"
Can some one please tell me how is it possible?
JIRA Version 6.x
There will be several ways for it.
1) Scripted custom field.
2) Script to calculate the "Expected End Date" on the post function of transition itself.
Hi Pushpkant, I don't have exact example for your query, but with the help of post function script it can be easily achieved. Cheers, Jayesh