Forums

Articles
Create
cancel
Showing results for 
Search instead for 
Did you mean: 

How to Copy aggregate value of customfields in to third customfield?

Pushpkant May 7, 2015

I have three fields

  • Task Start Date/Time
  • Original Estimate
  • Expected End Date/Time

I want value of "Expected End Date/Time" as "Task Start Date/Time + Original Estimate"

 

Can some one please tell me how is it possible?

 

JIRA Version 6.x

2 answers

1 accepted

0 votes
Answer accepted
Jayesh Baviskar
Community Leader
Community Leader
Community Leaders are connectors, ambassadors, and mentors. On the online community, they serve as thought leaders, product experts, and moderators.
May 7, 2015

There will be several ways for it.

1) Scripted custom field.

2) Script to calculate the "Expected End Date" on the post function of transition itself.

Pushpkant May 7, 2015

Hi Jayesh, Do you have any examples for this? Thanks

Jayesh Baviskar
Community Leader
Community Leader
Community Leaders are connectors, ambassadors, and mentors. On the online community, they serve as thought leaders, product experts, and moderators.
May 8, 2015

Hi Pushpkant, I don't have exact example for your query, but with the help of post function script it can be easily achieved. Cheers, Jayesh

0 votes
Pushpkant May 7, 2015

forget to mention this activity has to be done at the time of Issue Creation

Suggest an answer

Log in or Sign up to answer
TAGS
atlassian, atlassian community, loom ai, atlassian loom ai, loom, atlassian ai, record recaps of meetings, meeting recaps, loom recaps, share meeting recaps,

Loom’s guide to great meetings 📹

Join us to learn how your team can stay fully engaged in meetings without worrying about writing everything down. Dive into Loom's newest feature, Loom AI for meetings, which automatically takes notes and tracks action items.

Register today!
AUG Leaders

Atlassian Community Events