I have a Scrum board where swimlanes are organised by stories. Stories without subtasks will show up as a single card, while the ones with subtasks are represented as swimlanes, which is great.
What I would like to achieve is to show a story as a single card when it's closed, no matter if it has or has no subtasks. We use quite a few subtasks, and it would make our board much cleaner if closed items were represented as single cards.
If all the subtasks are closed, but the story is not, I still want to show it as a swimlane.
Is this even possible?
Thanks,
Tamas
Hi Tamas
Not sure if Jira had a switch to exactly meet your requirement. But I do see a workaround: Add a quick filter into your board to hide the Done sub-tasks, and display only Story and incomplete sub-tasks.
Online forums and learning are now in one easy-to-use experience.
By continuing, you accept the updated Community Terms of Use and acknowledge the Privacy Policy. Your public name, photo, and achievements may be publicly visible and available in search engines.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.