Hello all,
I am trying to mix two worklog sources into EazyBI and I need to limit data imported from JIRA.
I have JIRA TEMPO worklogs from 2013, but I want to import only the JIRA TEMP worklogs from 01/01/2016 until now.
Can anyone help me, how to set that in the EazyBI Jira import options?
Hi @Ricard Renalias and @César Koffi
Sorry for skipping this question.
I'm not sure what was available in 2018, but now we:
1. Import the Tempo worklog.
2. You can choose which issues to import (select project + JQL query) in the Import options.
We import all the work logs for selected issues.
We have an idea in our backlog to limit the work logs by date. That will be useful when the issue has a long.
If you have a specific problem or use case you want to discuss, consider writing to eazyBI support support@eazybi.com
Kind regards,
Ilze support@eazybi.com
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Online forums and learning are now in one easy-to-use experience.
By continuing, you accept the updated Community Terms of Use and acknowledge the Privacy Policy. Your public name, photo, and achievements may be publicly visible and available in search engines.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.