We have estimated the whole backlog in Stroy points.Is there a way of totalling it up in the Plan mode?
Create a sprint (no need to start it) and drag the marker to the end of the backlog. The totals will appear in the sprint marker. Delete the sprint when you have your answer if you don't need it.