Hello,
Why the view of Jira task an subtask is different, I can't add to Jira task an hour progress bar (estimated, tracked, left) which is easily added with admin rights to sub task.
Also how to add Complete % to task that it would be available to track % of a task complete and could be linked to Advanced Roadmap?
Hi @Agne Frolova - Did this answer your question?
Tasks are standard issue types (i.e. same level as Story)
Sub-task issue types (including Sub-tasks) are their own unique special level - hence different appearance in the UI.
You can see the logic and options for % completion here: https://confluence.atlassian.com/advancedroadmapscloud/tracking-progress-and-status-998651480.html
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Online forums and learning are now in one easy-to-use experience.
By continuing, you accept the updated Community Terms of Use and acknowledge the Privacy Policy. Your public name, photo, and achievements may be publicly visible and available in search engines.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.