I can´t find the option Active Sprints in my Project or I can´t active more than one sprint at a time..I need help. Thank you.

2 answers

1 accepted

0 votes
Answer accepted
Vishwas
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
February 17, 2022

Hey @u200353 

Based on the hosting type you are in either Jira cloud or Server/DC we can enable the parallel sprints as follows.

In case you are using cloud you can go to Administer Jira -> Products --> Jira software section and enable Parallel Sprints.  KB URL for same https://support.atlassian.com/jira-software-cloud/docs/use-parallel-sprints/

In case of server/dc hosting navigate to Administration --> Applications --> Jira Software Configurations --> Parallel Sprints. KB URL https://confluence.atlassian.com/jirasoftwareserver/using-parallel-sprints-938845513.html

Vishwas
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
February 17, 2022

In case of Kanban board follow Rishav's answer.

Like RISHAV KUMAR GUPTA likes this
u200353 February 17, 2022

That´s my problem..I checked and I have the parallel sprints option enabled, even this , I do not see the "active sprints" option in the project.

u200353 February 17, 2022

MicrosoftTeams-image (1).png

Vishwas
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
February 17, 2022

Okay, got it. One more question is it a Team Managed Project(TMP) or Company Managed Projects(CMP) ?

In case TMP parallel sprints concept is not there

Like u200353 likes this
u200353 February 17, 2022

It is TMP :(

Thank You!!

0 votes
RISHAV KUMAR GUPTA
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
February 17, 2022

Hi @u200353 it is because you are using Kanban board ,In that board no active sprint are there . There is active sprint only in scrum board company managed project (parallel sprint).

If possible can you send screenshot .

Thanks ,

Rishav .  