When viewing a parent Jira, the Sub-Tasks list does not include the issue number (key) for each sub-task. Is there a way to additionally display the issue number? Can this be added as an additional display field?
I am using Jira v6.3.15
Hi @Phyllis
You can edit the property 'jira.table.cols.subtasks' under Admin --> System --> General Configuration --> Advanced Setting. This is the path for Jira 7. Not sure of v6 but should be something similar.
Hi @Phyllis
Yes, you will need Jira global administrator rights for this.
Here is the documentation for Jira 6.3 Configuring Advanced Settings
Check the steps for 'jira.table.cols.subtasks' property and add the value issuekey there along with current options.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Online forums and learning are now in one easy-to-use experience.
By continuing, you accept the updated Community Terms of Use and acknowledge the Privacy Policy. Your public name, photo, and achievements may be publicly visible and available in search engines.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.