When I create a sprint for a team in Jira it does not appear in Portfolio unless I also drag a story into the sprint from Jira. When I hit Calculate stories are placed in the virtual sprints Sprint 2 etc) but I cannot move stories from the Portfolio sprints back to Jira unless I am working with the real Jira sprints... that didn't show up in Portfolio.
Is there a better way to get the sprint to show up?
Hi Amy,
Jira sprints, even empty, should show up in Portfolio. You may need to refresh and re-calculate your plan.
If that does not work, you can try to make sure the board showing the sprints is the same one that is used in your plan issue source.
Let us know how that goes.
Cheers,
The Portfolio Server team
Same issue here. Created 2 empty sprints on the Jira project board but does not show up on portfolio.
I can see current sprints but no new ones, so the source is referencing the correct board.
ONly workaround is to drag an issue into the sprint within the project, then calculate on portfolio and the sprint will show up.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Atlassian Government Cloud has achieved FedRAMP Authorization at the Moderate level! Join our webinar to learn how you can accelerate mission success and move work forward faster in cloud, all while ensuring your critical data is secure.
Register NowOnline forums and learning are now in one easy-to-use experience.
By continuing, you accept the updated Community Terms of Use and acknowledge the Privacy Policy. Your public name, photo, and achievements may be publicly visible and available in search engines.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.