Jira Burndown chart in EazyBI - Remaining Effort Estimation vs original Effort Estimation

itzik d July 25, 2022

Hi,

I have the EazyBI adds on and i'm trying to create burndown chart for fix version or even to sprint - but i have 4 teams managed in different boards.

 

How can i create timeline that shows cumulative Remaining Effort Estimations Vs Cumulative Original Effort Estimation?.

 

Any good idea how to track how much time is left to complete all tasks and if i'm on track?

Thanks in advance,

Itzik

 

 

2 answers

1 accepted

0 votes
Answer accepted
Florian Bonniec
Community Leader
Community Leader
Community Leaders are connectors, ambassadors, and mentors. On the online community, they serve as thought leaders, product experts, and moderators.
July 25, 2022
itzik d July 25, 2022

Thanks but i'm working with other fields: Remaining time and Original Effort  , and with fix version and not sprint

 

i tried to use this link:

 

https://eazybi.com/accounts/1000/cubes/Issues/reports/1037565-time-tracking-burndown-in-selected-version

 

but somehow i don't manage to see the version estimated guideline, and there's no "time within version " button in the chart.

 

Also i see the next:

 

The report shows the current trend of spent hours, optimal guideline for committed hours as well as remaining estimated hours history per selected sprint.
The report is built based on Hours spent and Remaining estimated hours which resembles original estimation at the beginning and changes over time when logging hours or estimates are updated.

0 votes
itzik d July 25, 2022

i tried to use this link:

 

https://eazybi.com/accounts/1000/cubes/Issues/reports/1037565-time-tracking-burndown-in-selected-version

 

but somehow i don't manage to see the version estimated guideline, and there's no "time within version " button in the chart.

 

Also i see the next:

 

The report shows the current trend of spent hours, optimal guideline for committed hours as well as remaining estimated hours history per selected sprint.
The report is built based on Hours spent and Remaining estimated hours which resembles original estimation at the beginning and changes over time when logging hours or estimates are updated.

 

Any idea what am i doing wrong here?

Lauma Cīrule
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
August 4, 2022

Hi @itzik d,

You are on the right track by using the report example. You can also export the report definition and import it to your account (https://docs.eazybi.com/eazybi/analyze-and-visualize/create-reports/export-and-import-report-definitions). This will re-create the report with all the measures in your account, you will only need to select the version.

Additionally, the 'Time within version' is a measure that needs to be created and selected in the report - then, you can add the filter to it and remove the measure while the filter remains. 

Here is a description of how to build the report for Sprint: https://docs.eazybi.com/eazybi/learn-more/learn-eazybi-through-examples/time-tracking-burndown-in-selected-sprint.

The version report would be similar only with Version dimensions and dates.

Lauma / support@eazybi.com