One of my PMs asked if there is a way to sequence tasks in a kanban project. The PM wants to have a start date and an end date for each task. I know i can create custom..question is also if I should use due date as the end date.
also the PM wants (this is the main thing) to be able to change the date on one task, and all tasks that were following it should change the dates accordingly. so this way, the whole remaining body of work within the epic would move forward in time automatically.
Hello,
In my opinion you should use DueDate.
About the other question the PM wants to have something similair to Microsoft Project. You should look at the plugin called BigPicture.
https://marketplace.atlassian.com/plugins/eu.softwareplant.bigpicture/cloud/overview
you are right, the PM got the idea from Microsoft Project. Thank you for this insight!
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Atlassian Government Cloud has achieved FedRAMP Authorization at the Moderate level! Join our webinar to learn how you can accelerate mission success and move work forward faster in cloud, all while ensuring your critical data is secure.
Register NowOnline forums and learning are now in one easy-to-use experience.
By continuing, you accept the updated Community Terms of Use and acknowledge the Privacy Policy. Your public name, photo, and achievements may be publicly visible and available in search engines.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.