I thought it would be easy, as JIRA supports both timeSpent and originalEstimate fields. However, it seems I cannot use these as operands:
PROJECT=A and originalEstimate < timeSpent
Is there any way how to do that, i.e. showing issues where original estimate was exceeded?
You need to compare versus workRatio. Please see: Is it possible to select all issues with timespent > timeoriginalestimate via advanced searching?
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Atlassian Government Cloud has achieved FedRAMP Authorization at the Moderate level! Join our webinar to learn how you can accelerate mission success and move work forward faster in cloud, all while ensuring your critical data is secure.
Register NowOnline forums and learning are now in one easy-to-use experience.
By continuing, you accept the updated Community Terms of Use and acknowledge the Privacy Policy. Your public name, photo, and achievements may be publicly visible and available in search engines.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.