how can i modify sprint dates in easy agile in program roadmap

Robert Enriquez
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
October 6, 2021

In creating a new PI in easy agile it allow you to select start date , sprint length and sprint count, but what if I have a modified sprint within a PI due to holidays. How can i modify the time box of any given sprint in PI 

1 answer

1 vote
Jared Kells
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
October 7, 2021

Hey Robert,

I'm Jared one of the developers on Programs.

Just to make sure I'm understanding correctly you would like one of the sprints to be a different length to account for holidays so for example with 3 sprints:

* Sprint 1 ( 14 days )

* Sprint 2 ( 12 days ) - 2 Holidays

* Sprint 3 ( 14 days )

Unfortunately we don't currently support having sprints of different lengths. It's a limitation of the product that we're aware of and it's on our backlog to improve.

On our team when we have public holidays we've been letting the sprint include the public holiday but we then manually adjust the capacities down by a percentage to account for the fewer work days.

If you're only interested in the dates from a Jira reporting perspective you can also manually edit the sprints in the standard Jira backlog. They won't be treated as shorter within Programs but they will be treated shorter throughout the rest of Jira.

Have a great day!

Cheers,

Jared Kells

Robert Blackadder
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
June 29, 2023

Hi Jared, I see this is still an issue.. it's now the last day of June 2023. How far back in the Backlog did you put this Feature  Sadly your answer does not work for me as I run a 5 Team ART, 4 use Scrum & 1 uses Kanban (Enabling Team). When you say "you can also manually edit the sprints in the standard Jira backlog." I can for the Scrum Teams, but the Kanban Team does not have a pure Jira Sprint Board. I have only created a pseudo-Sprint Board for them using your EA Program View. And I have only done this to identify and track Dependencies and Risks with the other Teams. So now I have 4 Teams aligned on the correct timeline & and 1 Team who are 1 week behind & no way to fix it until I create the Next PI.... Could you please have this escalated. As mentioned it's been wrong for a VERY long time and does need addressing. Thanks..

Elizabeth Cranston [Easy Agile]
Contributor
July 3, 2023

Hi @Robert Blackadder, thanks for reaching out. We agree that the workaround isn't ideal and are currently exploring a solution.

We have just sent you an email to book in a session to share your feedback with us over zoom. Hopefully we can have a more in depth conversation soon.

Thanks, Elizabeth - Senior Product Manager @ Easy Agile

Elizabeth Cranston [Easy Agile]
Contributor
December 28, 2023

Hi @Robert Blackadder

Hope you are doing well! 

Just wanted to let you know that we've released custom sprint lengths as part of the Easy Agile Programs v6.0.0 release!

Please check in out and let us know what you think.

Thanks, Elizabeth - Senior Product Manager @ Easy Agile

Like sely001 likes this
Jimmy Karlsson March 27, 2024

Hi @Elizabeth Cranston [Easy Agile] 

While this is a step in the right direction, we would still like to see full customizable dates for the sprints in Programs, not only weekly spans.

Optimally, when you create the sprints in Jira via EAP (when for example clicking on "Schedule team issues") it would be amazing if the dates configured in EAP actually got set in the Jira sprints as well. That would save a lot of manual work.

We are currently configuring the Jira sprints to our "correct" dates, but it is confusing for the end user when there are different dates in EAP compared to Jira.

Elizabeth Cranston [Easy Agile]
Contributor
April 1, 2024

Hi @Jimmy Karlsson 

Thanks for your feedback and explanation of your use case. It makes a lot of sense to enable this sync back to Jira sprints on the backlog. 

I have added your vote to the story on our backlog although at this stage I can't give an ETA at this stage.

Thanks for sharing your feedback and have a great day

Elizabeth - Senior Product Manager @ Easy Agile

 

Suggest an answer

Log in or Sign up to answer
TAGS
atlassian, atlassian government cloud, fedramp, webinar, register for webinar, atlassian cloud webinar, fedramp moderate offering, work faster with cloud

Unlocking the future with Atlassian Government Cloud ☁️

Atlassian Government Cloud has achieved FedRAMP Authorization at the Moderate level! Join our webinar to learn how you can accelerate mission success and move work forward faster in cloud, all while ensuring your critical data is secure.

Register Now
AUG Leaders

Atlassian Community Events