Sprint Board: Card view with sub-tasks

Tom Lindley April 7, 2017

New to Jira and trying to understand the active sprint view. I think I have things configured properly and get the stories for the sprints in the columns for the workflow. However, if a story has sub-tasks, then the story shows as a single line at the top above the other stories. If I filter out sub-tasks them the cards display they way I want, but I can't see the sub-tasks in the detail pane.

Any help on how to configure this view to get my results would be appreciated. Thanks.

1 answer

0 votes
Jared Dohrman {ANZ}
Contributor
December 17, 2020

Hi @Tom Lindley,

This is because your Scrum board is set to swimlane by Story. Try changing the Swimlane to Epic or Query; this will then group by Epic or Query (i.e. project = High)

Suggest an answer

Log in or Sign up to answer
TAGS
atlassian, out of office, loom, confluence, async collaboration, meeting recaps, remote teamwork, team alignment, knowledge sharing, AI-powered notes, productivity tools, workforce continuity, teamwork collection

Put your meeting notes on autopilot with Loom + Confluence

AI-powered meeting notes keep work moving even if you’re out of the office. Enjoy your well-deserved time off and return refreshed, confident you’ll catch up in no time.

Learn more
AUG Leaders

Atlassian Community Events