How can I add e.g. 7 days to the current date.
I wand to update a custom Field (Field Type: Date picker) with a Postfunction of the JIRA Suite Utiliy: Update Custom Field Value?
Thank for your help: The custom Field of Type "calculated Date" is my Resolution.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You will need to use the Transition Date/Time Field
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
I can't find the custom field type: Transition Date/Time Field To be more clear: I want to add e.g. 7 days to the current date, using the Postfunction "Update Custom Field".
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
It is not possible to add days using "Update Custom Field" post-function. You can only set it to current date value.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Online forums and learning are now in one easy-to-use experience.
By continuing, you accept the updated Community Terms of Use and acknowledge the Privacy Policy. Your public name, photo, and achievements may be publicly visible and available in search engines.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.