Hi,
I have an initiative + a few epics. See pic.
The 4th epic has still some work to do. How can I see how much work is still todo in the initiavitve. I see only the original estimate. (see pic 2, collapsed tree)
Hi,
Thanks for all help but I am not getting on wth this. Look at the image attached.
I have now added the estimated column but once again I do nog see it.
There is 20 h of work on the initiative, that is correct. 2 tasks one of 1 hour and one of 4 hours are still todo. the rest is done. I want to see on the initiative level that I have still got an estimated workload of 5 hours. as it is now I see 0.
So for the fifth item on your list (for instance), you would like to have the "Estimates (h)" column filled with "5" , right?
Could you check within Jira if both fields "Estimated" and "Remaining", which values do they contain?
Also when you click on the progress bar of this issue in Portfolio what do you see?
(And thank you to Maria for the link to the documentation it can of course help you :-) )
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
On the right side you have a cog icon which allows you to add columns. You can add the "Progress" column.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi, if you look at the second picture you will see that I have but this still does not show me how many hours of estimated work there is todo.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Oh alright, I didn't saw the second picture :-)
Well if you want to see the "Remaining estimate" that you have in the Jira Software issue, in Portfolio it is under the column "Estimates (h)". It's a bit confusing but the information is there.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Join the largest European gathering of the Atlassian Community and reimagine what’s possible when great teams and transformative technology come together. Plus, grab your Super Fan ticket now and save over €1,000 on your pass before prices rise on 3 June.
Register nowOnline forums and learning are now in one easy-to-use experience.
By continuing, you accept the updated Community Terms of Use and acknowledge the Privacy Policy. Your public name, photo, and achievements may be publicly visible and available in search engines.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.