Hello ,
I have added a gadget showing burndown chart . It displays Story Points on the y axis where as I want to see No of estimated and work hours Vs Date . How can I do that
You need to configure the agile board: Go to the Agile view, Board (upper-right corner) -> Configure. Then set Estimation to Original Time Estimate. This will however affect all users, it does not only concern your gadget. I do not think there is a way to set this only in the gadget.
https://confluence.atlassian.com/display/AGILE063/Configuring+Estimation+and+Tracking
Hi Eirik , I have found out the estimation setting from board configuration . The second part of my question is how to view resource wise burn down charts e.g. if there are 10 stories , each assigned to a different resource .How can i view resource wise burn down of the same sprint .Look forward to your kind response. Thanks.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
I don't think, or even hope, that this is possible. The burndown chart wasn't created to track individual progress, but that of a team.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Also , please suggest that how can we view user wise burn down charts .
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Online forums and learning are now in one easy-to-use experience.
By continuing, you accept the updated Community Terms of Use and acknowledge the Privacy Policy. Your public name, photo, and achievements may be publicly visible and available in search engines.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.